15 workers take 15 days to finish job,how many workers will finish job in 5 days?

回答 (6)

2015-06-06 2:10 pm
15 workers take 15 days to finish job,how many workers will finish job in 5 days?

(15 workers) * (15 days) = 225 worker-days to finish a job.

(225 worker-days) / (5 days) = 45 workers to finish a job
2015-06-06 1:12 pm
45 workers
2015-06-07 5:40 am
45.
2015-06-06 2:13 pm
Days____________Workers
15______________15
5_______________(15/5) (15) = 45

45 workers will finish job in 5 days
2015-06-06 1:10 pm
0.2728263689327467484845364574646022198386929673807057304868294539795659386649967403056820387402664829475753478735719287293667393928636856874689326863890438468845674534883226983775225965757642380953274588226913414117789453576378249934798348822573587
2015-06-06 1:30 pm
15 workers.