contract law.

2014-11-18 6:58 am
個CASE係A請B幫佢裝修五間屋,完成後會俾返五十萬裝修費俾B,咁B係七月開始裝修.但當B裝修到第二間屋時,發現完工進度要比想像中遲.同埋問A要多五萬去買額外既材料.A就同意會將依五萬加入去個五十萬到,.另外同B講如果B可以係8月25號完工到.就會再俾多額外十萬俾B.咁最後B係8月20完工.但A話佢有財政困難.要求B接受五十萬in full settlement of A account.B接受左.但後尾發現原來A既財政困難其實唔係咁嚴重,於想想問A拎返個十萬

問題如下
1.was a promise to pay the extra $50,000 a binding variation of the contract?

2.was a promise of an extra $100.000 if the work is completed by 25 agust a binding varation of the contract?

3.is b promise to take the $500,000 in full settlement binding on b ?

回答 (1)

2014-11-22 7:13 am
✔ 最佳答案
This is homework. I will not answer it for you. You should work it out through your study. Furthermore, a definite answer cannot be drawn since both yes and no could be the answers for those 3 questions.

The case you should also consider are these:
Stilk v. Myrick 1809 c/f Harris v. Watson 1791
Williams v. Roffey Bros & Nicholls (Contractors) Ltd. 1990
Foakes v. Beer 1984

The area you should also consider is:
Consideration

收錄日期: 2021-04-25 22:25:33
原文連結 [永久失效]:
https://hk.answers.yahoo.com/question/index?qid=20141117000051KK00098

檢視 Wayback Machine 備份