In construction site,a pile driver is used to drive a pile into the soil. It is released
from rest at time t=0.Fig.b(net force against time graph) shows how the net force F on the pile driver varies with t.Take upward as positive.Ignore air resistance.
(The graph:t=0s-3s, F=-30000N.t=3s-4s,F=100 000.After 4s,F=-30000.)
a)find the mass of the pile driver.
b)show that the momentum of the pile friver just before the impact is
-90 000 kg m s^-1.
c)find the momentum of the pile driver just after the impact.