1. The Operations Director is expected to return to the US for a period before going back out to Africa to oversee the recruitment of the operating staff; a process which is expected to last 5 week.
請問是Operation Director 回美國5周, 還是recruitment 需要用5周的時間?
2. The overseas team will divide to oversee the two activity streams necessary to get the new facility up and running.
請問何解?
3. If the interest on money raised from the sale of the building saved $800/per day from the cost of the project, discuss how much could be saved by crashing and describe which activities would be affected give the following information...
請問何解? 特別是"If the interest on money raised from the sale of the building saved $800/per day from the cost of the project"...及為何crashing會與慳$有關?
thx!