The completion time of a building depends on whether the carpenters and plumbers working on its construction go on strike. The probability of delay in completion are @, 8@, 16@ and 1 if
neither go on strike,
if the plumbers alone go on strike,
if the carpenters alone go on strike and
if both go on strike, respectively, where 0<@<1/16.
The plumbers have a probability $ of going on strike. If the plumbers are on strike, the carpenters have a probability 3$ of also being on strike, where 0<$<1/6. Similarly, if the carpenters are on strike, the plumbers have a probability 6$ of also being on strike. Determine the probability of delay in completing the building.