NPV vs IRR

2009-08-15 7:29 am
ABC Company is considering to use a different evaluation criteria,
namely the internal rate of return method (IRR),
in making a capital budgeting decision in future.
Explain to ABC Company whether Net Present Value method (NPV)
is a better criteria than IRR method.

回答 (2)

2009-08-15 8:01 am
✔ 最佳答案
IRR係回報率,一般只要高過要求回報率,這項目都可做,NPV就只要是正數便可做.一般計獨立項目時,用任何一個都冇分別.

但如果公司要係兩個項目,只做一個,例如做晒兩個吾夠錢,便要比較兩個項目,那個較吸引,這時便要用NPV,以最大為優,因為代表賺取最高收入,即使這個項目IRR較另一個項目少.








2009-08-17 18:07:29 補充:
IRR is focused on how much percentage the project can earn, when the project has the hurdle rate would be smaller than IRR rate , this project should be taken.

NPV is focused on how much money the project can earn, when the NPV is over zero,this project should be taken.

2009-08-17 18:07:55 補充:
In general ,IRR and NPV will have the same result,because when the project can make profit , it means this project's IRR rate must be higher than huddle rate. it also means when this project's IRR rate smaller than hurdle rate , and it's NPV must be negative.

2009-08-17 18:08:39 補充:
In the reality . company can not take all project by limited capital. so company have to pick up the better one.

2009-08-17 18:09:01 補充:
Company may encounter the situation like this ,project A' IRR would be 20%, NPV would be $1000. Project B ' IRR would be 15% , NPV would be $1200 .
In this case , company should pick up project B by higher amount.

2009-08-17 18:09:16 補充:
why the conflict appears on some case like above ? because IRR is ignoring any investment amount . so when project B has a bigger investment amount than
Project A ,Project B can be better than Project A even Project B' IRR smaller than Project A
2009-08-16 7:38 am
敬請閣下可否把中文翻譯英文 感謝 多謝 謝謝 ^.^


收錄日期: 2021-04-17 00:08:04
原文連結 [永久失效]:
https://hk.answers.yahoo.com/question/index?qid=20090814000051KK02445

檢視 Wayback Machine 備份