Here comes a Simultaneous Linear Equations in 2 Unknowns,please List out the the equations and show a clear working steps
Q:To produce the sail and the holder are the 2main procedures to produce an umberlla.In a factory,each worker can make a sail in 3min or make a holder in 2 min.If there are 10 workers,how should we assign the workers so that the procedures in making the sail and holders can be finished at the same time?
A: 6 workers should make sails and 4 workers should make the holders
Please list out the 2 equations