✔ 最佳答案
我剛剛完成的寫字樓工程(約4,500 sft) 總額約HK$ 2M for your budget.
設計期 30日 及 施工期 45 日
1Design & Construction drawing ($ 80,000)
2Setting out ($ 6,000)
3Electrical work installation ($ 250,000)
4MVAC system installation ($ 150,000)
5Fire service installation ($150,000)
6Data & Voices ($ 75,000)
7Suspended Ceiling ($ 75,000)
8Glass partitions ($ 50,000)
9Doors ($ 100,000)
10Joinery ($ 100,000)
11Ceiling cornice & skirting ($ 75,000)
12Wall finishes ($ 90,000)
13Gypsum board ceiling ($ 75,000)
14Plumbing & driange ($ 45,000)
15Security system ($ 35,000)
16Marble flooring ($ 75,000)
17Carpet tiles ($ 80,000)
18System furniture / Loose furniture ($ 250,000)
19IT ($ 90,000)
20Blinds ($ 60,000)
21General cleaning ($ 5,000)
22Mover cost ($ 40,000)