政府刊物介紹新完成私廈或屋苑之驗收程序及時間表

2007-07-16 5:52 pm
政府刊物介紹地盤起貨 新完成大廈或屋苑之驗收程序及時間表

我想問幾時可以入以下之表格

包括水紙,wwo form 46
驗洧防 FS form 501
及BD FORM 13 及 FORM 14 有乜分別

請詳細說明及加以例證

THANK YOU

回答 (1)

2007-07-16 10:22 pm
✔ 最佳答案
WWO46 - It is plumbing proposal in which the last part of it the licensed plumbing shall submit to WSD for completion of works and ask for WSD inspection. The certificate issued by WSD is pre-requisite for occupation permit.

FS501 - Submit to FSD when all FSI is completed. The certficate is pre-requisite for occupation permit.

BA13 is for New building works and OP shall be issued where BA14 is for completion of building works resulting NO new building.
參考: Experience


收錄日期: 2021-04-18 14:21:22