1) there are 65 wokers in a project of digging and removing mud from a working site . Each worker can dig 2.5m of mudor remove 30m mud everyday . If the surpervisor of this project wants to allocate the workersin such a way that the mud dig every day can be remove on the same day,find an appiopriate method of allocating the workers?

Let X be the no.of workers who dig , then the no. of workers who is move mud is 65-X.

回答 (4)

2006-10-30 11:39 pm
✔ 最佳答案
1.
Let the number of workers digging the mud be x
2.5x = 30(65 - x ) .
2.5x = 1950 - 30x
32.5x = 1950
x =60
the number of workers digging the mud should be 60
the number of workers removing the mud should be 5

2006-10-31 12:13 am
2.5x = 30(65-x)
2.5x = 1950-30x
32.5x = 1950
x = 1950/32.5
x = 60

60 workers should dig , (65-60)=5 workers should move mud
2006-10-30 11:46 pm
2.5X = 30(65-X)
2.5X = 1950-30X
32.5X = 1950
X=60

the no.of workers who dig is 60
the no. of workers who is move mud is (65-60)=5
參考: ME
2006-10-30 11:43 pm
let x = workers who dig
65-x = workers who move

2.5x = 30(65-x)
2.5x = 30(65) - 30x
2.5x + 30x = 30(65)
32.5x = 1950
x = 1950/32.5
x = 60

60 workers should dig, 5 workers should move